Completion (including delay and cost overrun) risk

Port Port

Description (What is the Risk)

The risk of commissioning the asset on time and on budget and the consequences of missing either of those two criteria.

Risk Allocation (Who typically bears the risk)

Allocation: Public Private Shared
Rationale

The Private Partner will bear principal responsibility for delay and cost overrun risk, and will typically manage this through the engagement of a suitable EPC contractor.

The principal risk arising out of delay will be the loss of expected revenue, the ongoing costs of financing construction, holding costs of other contractors and extended site costs.

The Private Partner is best placed to integrate complex civil works, the delivery and commissioning of rolling stock, despatching and operations, and preventative and lifecycle maintenance to ensure a reliable and punctual service for an efficient price. This may be managed through a single EPC joint venture or by the Private Partner managing a series of works, supply and operation/commissioning contracts.

The Private Partner will be expected to demonstrate adequate system performance before it is given permission to operate the system.

Mitigation Measures (What can be done to minimize the risk)

The Contracting Authority may wish to implement a multi-staged completion process to ensure the Private Partner begins receiving payment for its design and construction services once significant components of the project are substantially completed. This can help increase cash flow during construction, reduce the Private Partner's financing costs and incentivize the phasing of construction works in order to ensure critical components are completed on time. Financial penalties and liquidated damages can help enforce construction deadlines.

The combination of (i) incentives or penalties for timely completion and (ii) the implementation of a 'longstop date' (a date which is pegged to a prescribed time period after the scheduled completion date) will create the necessary tension to incentivize timely completion while allowing the Private Partner a reasonable amount of time to meet its contractual responsibilities in spite of delays before the Contracting Authority can terminate the project.

The Contracting Authority may also consider the inclusion of a look forward test to trigger a default if an independent party certifies that completion will not be achieved by the longstop date.

Government Support Arrangements (What other government measures may be needed to be taken)

The Contracting Authority may have a critical role to play at stages of the construction, testing and commissioning process in terms of ensuring that any rights that it has to comment on design development and testing results do not adversely delay the project.

The Contracting Authority may allow for certain relief events, delay events or force majeure events where delays or cost overruns have arisen from either the fault of the Contracting Authority, or no-fault events.

Similarly the Contracting Authority may need to take responsibility for delays caused by the failure of public bodies to issue necessary consents in good time.

Comparison with Emerging Market

In developed markets, enforcement of construction deadlines and budgets may be easier as the Private Partner will typically have more experience and reliable resources.

Back to Port

Description (What is the Risk)

The risk of commissioning the asset on time and on budget and the consequences of missing either of those two criteria.

Risk Allocation (Who typically bears the risk)

Allocation: Public Private Shared
Rationale

The Private Partner will bear principal responsibility for delay and cost overrun risk, and will typically manage this through the engagement of a suitable EPC contractor.

The principal risk arising out of delay will be the loss of expected revenue, the ongoing costs of financing construction and extended site costs.

A key integration risk on port projects is the procurement and installation of cranes and other goods handling machinery. These may be provided by an operator or through long term leasing arrangements and may sit outside the EPC contractor's scope.

Mitigation Measures (What can be done to minimize the risk)

It may be difficult for the Private Partner to mitigate these integration risks solely through contractual risk allocation, as the financing cost / lost revenue impact is typically very high compared to the individual component parts of the project that can affect this. Ensuring that the programme has sufficient float periods for all critical stages and that parties are incentivised to work together to achieve the common deadlines may be more effective strategies.

Government Support Arrangements (What other government measures may be needed to be taken)

The Contracting Authority may have a critical role to play at stages of the construction, testing and commissioning process in terms of ensuring that any rights that it has to comment on design development and testing results does not adversely delay the project.

Similarly the Contracting Authority may need to take responsibility for delays caused by failure of public bodies to issue necessary consents in good time.

Comparison with Developed Market

An additional concern for the Private Partner to manage in the context of delays will be whether the Private Partner will breach any minimum throughput guarantee owed to the Contracting Authority (see performance risk section).