Force majeure risk

Solid waste collection, disposal, landfill and recycling Solid waste collection, disposal, landfill and recycling

Description (What is the Risk)

The risk that unexpected events occur that are beyond the control of the parties and delay or prohibit performance.

Risk Allocation (Who typically bears the risk)

Allocation: Public Private Shared
Rationale

Force majeure is a shared risk and there will be a fairly well developed list of events that entitles the Private Partner to relief.

Typical events include (i) war, armed conflict, terrorism or acts of foreign enemies; (ii) nuclear or radioactive contamination; (iii) chemical or biological contamination; (iv) pressure waves caused by devices traveling at supersonic speeds; or (v) discovery of any species-at-risk, fossils, or historic or archaeological artefacts that require the project to be suspended for a period of time.

Force majeure events occurring during construction will also cause a delay in revenue commencement. The ability of the Private Partner to bear this for uninsured risks will be limited, and the Contracting Authority will typically have to bear the risk after a certain period of time or level of cost has been exceeded.

During operations, the impact of the force majeure event will depend on whether the project is availability based (where relief from KPI penalties may be required) or is demand-based (where an element of gatefee subsidy may be required).

Mitigation Measures (What can be done to minimize the risk)

Project insurance (physical damage and loss of revenue coverage) is the key mitigant for force majeure risks that cause physical damage.

On an availability based project, the risk of disruption as a result of no-fault events could be mitigated by relaxing the performance thresholds (e.g. requiring a lower level of acceptable service, which then allows the Private Partner to take the risk of a certain number of day-to-day adverse events typical to a project of this nature but without incurring performance penalties).

The risk of missing recycling or landfill reduction targets would shift back to the Contracting Authority.

Government Support Arrangements (What other government measures may be needed to be taken)

Generally speaking, where parties are unable to agree on a way forward following a force majeure event, an amount of compensation should continue to be payable by the Contracting Authority to the Private Partner in order to service the Private Partner's debt obligations during the course of the event. Where the project is terminated, the Contracting Authority may be required to fully compensate the Private Partner for debt owed to senior lenders. Whether the debt will be kept whole in such a scenario, will be a key area of focus for prospective lenders as part of their initial credit assessments.

Comparison with Emerging Market

On developed market transactions, the Contracting Authority typically compensates the Private Partner, only for its outstanding debt (but not for its expected rate of return) for termination arising from a 'natural' force majeure.